Employer: CDIG – China
Details: All Civil works related to Aqaba Oil and LPG Storage Terminal consisting of Site Excavation and Backfilling, Tank Foundation, Buildings, Infrastructure and Roads.
Commencement: May, 2014
Completion: February, 2018
Employer: FLSmith RAHCO Inc
Details: Replacement of Electrical and Mechanical Equipments for Harvesters 5 and 6 including painting works.
Commencement: January, 2017
Completion: January, 2018
Employer: Arab Potash co. (APC)
Details: Mechanical Equipment Installation with its related Electrical and I&C Works. Steel Structure Works, Civil Works, Fabrication and Welding.
Commencement: September, 2016
Completion: October, 2017
Employer: FLSmith RAHCO Inc
Details: Electrical Work, Fabrication and Equipment Erection and Instrumentation Works one Harvester No. 12 for APC in AlSafi – Jordan and Floating Pipeline.
Commencement: February, 2013
Completion: May, 2014
Employer: Jordan Bromine Co. – Kentz Overseas
Details:Electro-Mechanical Equipment Erection including Piping and Instrumentation for Phase 2 of Petra Expansion.
Commencement: December, 2012
Completion: April, 2013
Employer: FLSmidth RAHCO Inc
Details: Fabrication, Equipments Erection, Electrical and Instrumentation Work of one Harvester No. 4 in APC.
Commencement: November, 2012
Completion: May, 2013
Employer: DIWACO–GAMA
Details: Pumping station at Madaba, Dabouk Reservoir Site and Abu Alanda Reservoir Site. Mechanical, Electrical and Civil Works related to Conveyance Pumps, Piping, Flow Control Station, Chlorination System, Switchgear (MV & LV), SCADA, Instrumentation, Cable Raceways, Cables and Valve Chambers.
Commencement: December, 2011
Completion: August, 2013
Employer: FLSmith RAHCO Inc
Details: Electrical Work, Fabrication and Equipment, Erection and Instrumentation Works of one Harvester No. 11 for APC in AlSafi – Jordan and Floating Pipeline.
Commencement: November, 2010
Completion: December, 2011
Employer: Jordan Bromine Company Limited
Details: Bromine Pipeline Installation of 4Km GRE Brine Pipe including all Concrete foundation and supports..
Commencement: April, 2011
Completion: July, 2011
Employer: Jordan Bromine Company Limited
Details: JBC Factory extension Adding Tetra Bromine Unit which included Equipment, Piping and Instrument Installation.
Commencement: February, 2011
Completion: May, 2011
Employer: ALSTOM POWER CENTRALES, Saudi Arabia
Details: Structural Steel, Mechanical Equipment, cladding Flue Gas Ducting, Piping erection Works.
Commencement: October, 2009
Completion: February, 2011
Employer: FLSmdith RAHCO INC. – ARAB POTASH COMPANY
Details: Fabrication of 2 Nos. Potash Harvesters for APC in Jordan including Electro-Mechanical Works and Piping.
Commencement: March, 2008
Completion: May, 2009
Employer: FLSmidth RAHCO INC. – ARAB POTASH COMPANY
Details: Electrical Works for Two Harvesters for APC in JORDAN.
Commencement: September, 2007
Completion: February, 2008
Employer: Magnesium Oxide CO. JORDAN
Details: Identification and procurement of outstanding material requirements, installation of all outstanding piping and mechanical equipment works, including insulation and cladding, pre-commissioning and commissioning assistance.
Commencement: September, 2002
Completion: March, 2003
Employer: Hitachi Plant Engineering & Construction Co. LTD
Details: Construction of all Mechanical Plant, Equipment and Piping, etc. for the Improvement of ZAI Water Treatment Plant for the Water Authority of Jordan Ministry of Water & Irrigation.
Commencement: October, 2000
Completion: November, 2001
Employer: COMUSAT – Orange
Details: Civil works including GSM Towers, Equipment Foundations, Fencing, Electro-Mechanical Erection Works.
Commencement: March, 2000
Completion: July, 2000
Employer: Chiyoda Corporation
Details: Erection of all Equipment as well as Installation of the following Work: Instrumentation Electrical Ducts and Chutes Piping Painting & Insulation.
Commencement: June, 1995
Completion: December, 1996
Employer: Telecommunication Corporation (TCC) Jordan
Details: Complete Civil and Electro-Mechanical works for the Intelsat Standard “A” Earth Station designated
Baqa-4.
Commencement: May, 1994
Completion: October, 1995
Employer: Bouygues – Jordan Phosphate Mines Co
Details: Up-Grade and Increase the Production of the Existing & Operating Phosphoric Acid Plant..
Commencement: May, 1993
Completion: December, 1993
Employer: Water and Electricity Authority – Government of Abu Dhabi – U.A.E
Details: Installation of 6 Nos. Multi Stage Flash Desalination Units at a Total Capacity of 10,000 m³ Per Day.
Commencement: November, 1985
Completion: May, 1987
Employer: Al Bassam Global Corporation
Details: Supply, Installation and Commissioning of Civil and Electro-Mechanical Works for the Construction of Ready Mix Concrete Plant.
Commencement: November, 1980
Completion: May, 1981