Employer: Aqaba Container Terminal Co.
Details: The Construction of the Original Wharf Works consisting of Piles, HDPE and Steel Jackets installation, repair of Soffit Slab, Beams, Pile Caps, repair of deck slab concrete and Installation of Fibrwrap System on the main bulkhead Quay Wall.
Commencement: December, 2015
Completion: December, 2016
Employer: Aqaba Development Company
Details: Design and construction of an LNG Jetty with approach Trestle, in Joint Venture with BAM International, including the required Electro-Mechanical Services and Metering System, for handling the LNG from FSRU to the tie in point. In addition to Buildings, Infrastructure and Landside Civil Work.
Commencement: January, 2014
Completion: July, 2015
Employer: Aqaba Development Company
Details: Design and construction of 1Km Berth in Joint Venture with BAM International, the work consists of dredging, rock armouring, supply and installation of tubular steel and sheet pile, 20,000m² of in-situ and precast reinforced concrete.
Commencement: March, 2012
Completion: March, 2014
Employer: Aqaba Container Terminal – Bam International.
Details: Land Side Works Consisting of Earthworks (Excavation and Backfilling). Precast Concrete Works, Infrastructure (Fire Fighting, Electrical Services and Drainage), and all Structural Paving Works of 5,000m2 storage yards.
Commencement: June, 2011
Completion: October, 2013
Employer: Aqaba Container Terminal Co
Details: All Civil Infrastructure Works for Crane Rail at Aqaba Container Terminal including Rail Welding and Installation.
Commencement: June, 2009
Completion: February, 2010
Employer: Aqaba Container Terminal Co
Details: Pavement and Infrastructures including surface water drainage, Fire Fighting and Electrical services for 80,000m2 of Container Terminal.
Commencement: September, 2005
Completion: March, 2007
Employer: Amman Resources – Jordan Cement Factories
Details: Turnkey job including design, supply and construction of a cement export terminal of 30,000 MT capacities at Aqaba Port.
Commencement: December, 1991
Completion: October, 1992